evaluation
Evaluation
Pre-production
is all about managing the finances, logistics and creative choices that need to
be made to make a film. This stage in filmmaking is the most crucial as it
effects every aspect of the film and can easily decide the quality of the
finished product. Effective project management is all about ensuring that the
production of the film runs smoothly, on schedule, and that no aspect is
forgotten about. My aim for the project is to make sure all those things
happen.
Finances
I feel that
my management of both finance and budgeting were professional and efficient.
Very little money was wasted and we managed to make the film on a low budget.
An important part of keeping the expenses low was being organized and planning,
ahead of time, what funding methods we should use. By evaluating, in
pre-production, the advantages and disadvantages of various sources of funding
we managed to find a way to get enough money without much hassle. I figured out
that a bank loan has its drawbacks; with repaying the loan and we were unlikely
to obtain private funding due to the fact that there is no profit in the final
outcome and the funding would be little anyway as it’s a small-scale project so
private investors would see it as a waste of time. Here is a table evaluating them
(below).
Therefore, I
decided to fund it myself as it was the easiest and quickest method and I knew
the only drawback would be the fact that I’m spending money, which I was
prepared to do. This overall meant that we had to be careful to prioritize
money for costumes and props and other resources and not spend too much money
on things that weren’t necessary. I believe in this aspect of production it was
incredibly successful as we ran into little issues. The only negative impact on
my project is that we can’t go over budget because it’s my money but this does
mean that I can spend however much I want without making myself poor.
Logistics
Logistics is
the organizational aspect of production and it is vital that it is done
effectively as if it isn’t at an industry standard, then the entire production
can fall apart due to a lack of direction, coordination and organization.
Therefore, if the logistics are done without careful consideration then you
could miss crucial steps in production which could lead to the final outcome
missing scenes or with segments with rushed editing which wouldn’t be
professional and therefore wouldn’t meet the aims. A key part in this is the
action plan. This plan is the first thing that I did in pre-production as it
outlines all of the steps in pre-production that need to be taken and in what
order. This also outlines where I have gaps in my schedule designed to allow me
to reshoot if necessary and give me extra time for editing if I run behind
schedule. This action plan is aided by my risk assessment and contingency plan
which both outline problems that could occur and how to solve the in an
effective way.
As you can
see this action plan is very well thought out and user friendly to read with
the weeks outlined to notify the production team how long it should take to
complete each given task. This effectively makes a checklist that allowed us to
clearly see if we were behind or ahead of schedule and allowed us to
effectively foresee any setbacks. Whenever we started the next step the first
thing we did was check the action plan making it essential to the entire
filmmaking process. We always did this to keep on track and never miss any
steps.
Inevitably,
setbacks occurred. We had two imperative outlines for how to circumvent these
catastrophes in the form of risk assessments and contingency plans.
|
Potential
problem |
contingency |
|
Equipment
damaged or lost. |
If we
are unable to use the equipment for example the cameras, we can use our phone
cameras as a last resort. The camera quality is good enough and the
microphones can even record in stereo now so we could even use them for sound
if any microphones are unusable. If the equipment is damaged and it’s our
fault we may have to pay the loaners some compensation which
would be a blow to our budget. |
|
Last
minute rewrites. |
I will
most likely only rewrite the script if I already have thought of the big
changes. If I have ideas for extra lines they will probably be added to the
script and tried during filming after the main shooting has done for the
scene. This allows me to then edit these parts out if I change my mind later.
Bigger changes like new scenes set in new locations with a slightly different
plot for the overall film will be considered more and the logistics of being
able to make these scenes will be thoroughly evaluated. The extra weeks may
also be obviously used. |
|
Loss of
footage |
Depending
on the amount of footage lost there will be reshoots needed which
is accounted for in the action plan with an extra week in between the editing
phase for any necessary reshoots. These reshoots may also be used for any
changes in the story. |
|
Staff/cast
unavailability |
Depending
on the reason then there can be a rescheduling later on in the weeks of
filming. If cast will be unavailable unexpectedly for a significant amount of
time to the point where rescheduling is impossible then they may be recast.
If nobody can be found a crew member or myself will step in and
do the job ourselves. |
|
running
behind schedule |
If
we run behind schedule then it we have extra time to reschedule for extra
shoots. If the editing process is what is taking too long then the extra two
weeks will be used as extra editing time. |
As you can see
this, contingency plan outlines the potential problem that can occur. This was when we needed to reshoot as it outlined the
way we should logically move forward in a professional manner. In conclusion
this contingency plan was crucial to staying on track and it was incredibly
vital to keeping the production industry standard and without it the entire final
stages of the production wouldn’t have been as organized in, what I consider,
the most vital stages of the project. This is because if these risks aren’t
planned and they happen then the problem may not be handled as effectively
which can cause the film to be delayed, rushed and the quality of the film
could not be an industry standard.
Here is my risk assessment
and after is a professional example.
I believe
that my risk assessment is as detailed as the example however, the professional
example has information such as the site that its is supposed to be assessing
making it more organized within the entire project.
If I didn’t have
this risk assessment then I could be liable for any damages to people or rented
equipment and I would have to pay compensation which can impact the entire
project as I wouldn’t be able to invest as much money in the project for extra props
and equipment. This risk assessment also outlines what needs to be done to
minimize the risk so having it would also reduce the chance of injury to the
cast and crew.
Creative
The creative
aspect of production mainly consists of the story and how it should be
presented to the audience for example what angles and shots will be the most
effective at presenting the story in its full glory to the audience. If the
film ends up being boring, confusing or just plain awful then the creative
process is flawed. The key to success in the creative component is trying to
blend the vision of the writer alongside what the director and editors choose
to cut and keep. This is because what makes an excellent book, story or script
doesn’t necessarily work well on the big screen due to filmmaking concepts like
pacing. To circumvent this we used a film treatment to establish basic
guidelines for what the creative vision of the film is to allow us to ensure we
are heading in the right direction.
This
treatment also gives us simple character descriptions with room for their
motivations and charisma to be fleshed out in the script. We also have a run
time which allows the director and editors to cut and alter the story to make
the scenes flow in a professional manner without making the film too long and
avoiding the film from dragging on.
Here
is a professional film treatment to compare to my own.
This treatment is a
lot more summarized and easier to understand than my own due to the layout and presentation
making the information clear to the reader. They can quickly see each section and
find the necessary information that they are trying to find where mine isn’t as
clear to see the subheadings as they are not bold and therefore at a glance
they are hard to see.
Conclusion